ATL West Deck  Milestone Dates: 

Current Procurement Bid due dates:

Mechanical/Plumbing & Electrical  - July 14th, 2017 

Turnkey Concrete  - August 3rd, 2017 

Drawing Package Release dates: 

Design Development drawings - June 16th, 2017 

Issued for Consutrction Deep Foundation Drawings - June 16th, 2017 

Issued for Procurement Superstructure Drawings - June 23rd, 2017 

95% Construction Documents Issued - TBD

Roadway / Bridge Documents Issued - TBD

Additional Dates: 

Project Information Session #3 - TBD

*Refer to the Bid Package Updates tab for trades that have been purchased to date, current procurement efforts and future procurement dates